Query ID,BOQ ref,Issue,Decision owner role,Instructional resolution,Document issued,Status Q-001,08.15,BOQ 18 sets vs current schedule 20,Project design lead / authorized buyer,Use 20 sets for supplier enquiry; cost manager retains original BOQ and addresses contract adjustment,RFQ R02 + D01 R03,closed example Q-002,09.04,Net measured area vs order allowance and stock,Buyer / designer,"100 m² net + 8 m² example allowance, round full cartons; add 2 spare cartons",RFQ R02 + F01 R03,closed example Q-003,12.07,Installed item vs cabinet supply-only enquiry,Package buyer,"Cabinets/panels/hardware included; countertops, appliances and installation separate",RFQ R02 + K01 R02,closed example